Storing of Cement on Site - Guidelines
Store Cement in a dry building, leak-proof and as moisture is proof is possible.
There should be a base number of windows in the capacity building.
Stack the Cement bags off the floor on wooden planks in such a way, so that it is about 150 mm to 200mm above the floor.
The floor might involve lean concrete or two layers of dry blocks laid all around the combined earth.
Keep a space of 600mm overall round between the outside walls and the stacks.
Stack the cement bags close to each other to reduce the circulation of air.
The Height of the stack should be more than four bags length of 3 metres.
In stacks above 8 sacks high, the concrete packs ought to be organized on the other hand length-wise, and across, to integrate the stacks and limit the risk of bringing down.
Various sorts of concrete should be stacked and put away independently.
For more information visit now: https://www.buildersmart.in/blogs/Storage-of-cement
Gypsum plastering is an environmental friendly alternative to traditional sand-cement application for internal plastering surfaces. Gypsum plastering ...
Safety on construction sites is not just about following rules—it’s about protecting lives. By implementing these essential safety measures, construct...
Abuildtech offers high-quality prefabricated site offices, perfect for on-site project management and coordination. Our site offices are designed to b...
Explore NCUI, the best online shopping site in India, for a diverse range of authentic handicrafts and organic products. Enjoy a seamless shopping exp...
More Details